After the emulsified asphalt equipment has been used for a long time, it needs maintenance. There are several points to note when adjusting the emulsified asphalt equipment:
1. During use, regular maintenance should be carried out as appropriate according to the processing materials;
2. For the maintenance and use of the motor, please refer to the motor instruction manual;
3. Most of the random spare parts are national standard and department standard parts, which are purchased all over the country;
4. The colloid mill is a high-precision machine with a line speed of up to 20m/second and a very small grinding disc gap. After overhaul, the coaxiality error between the housing and the main shaft must be corrected with a dial indicator to ≤0.05mm;
5. When repairing the machine, it is not allowed to be directly knocked with an iron bell during the disassembly, reassembly and adjustment process. Use a wooden hammer or a wooden block to knock gently to avoid damaging the parts;
6. The seals of this machine are divided into static and dynamic seals. The static seal uses an O-type rubber ring and the dynamic seal uses a hard mechanical combined seal. If the hard sealing surface is scratched, it should be repaired by grinding on flat glass or flat castings immediately. The grinding material should be ≥200# silicon carbide grinding paste. If the seal is damaged or cracked seriously, please replace it immediately.

Rated 4.7/5 based on 258 customer reviews
Share:
Content

After the emulsified asphalt equipment has been used for a long time, it needs maintenance. There are several points to note when adjusting the emulsified asphalt equipment:
1. During use, regular maintenance should be carried out as appropriate according to the processing materials;
2. For the maintenance and use of the motor, please refer to the motor instruction manual;
3. Most of the random spare parts are national standard and department standard parts, which are purchased all over the country;
4. The colloid mill is a high-precision machine with a line speed of up to 20m/second and a very small grinding disc gap. After overhaul, the coaxiality error between the housing and the main shaft must be corrected with a dial indicator to ≤0.05mm;
5. When repairing the machine, it is not allowed to be directly knocked with an iron bell during the disassembly, reassembly and adjustment process. Use a wooden hammer or a wooden block to knock gently to avoid damaging the parts;
6. The seals of this machine are divided into static and dynamic seals. The static seal uses an O-type rubber ring and the dynamic seal uses a hard mechanical combined seal. If the hard sealing surface is scratched, it should be repaired by grinding on flat glass or flat castings immediately. The grinding material should be ≥200# silicon carbide grinding paste. If the seal is damaged or cracked seriously, please replace it immediately.

Inquiry


    More Road Maintenance

    Some of the equipment of emulsified modified bitumen equipment are as follows. The specially made bitumen filter can effectively filter the residues and dirt in the high-temperature culture medium bitumen to avoid damage to the subsequent equipment. The emulsified modified bitumen equipment adopts a spiral plate type or a shell and tube heat exchanger to quickly heat the culture medium bitumen through high-temperature heat transfer oil to meet the needs of the production process. The emulsified modified bitumen equipment is heated in the storage tank to prevent the bitumen from aging due to long-term high-temperature heating and exposure to the air. The sulfate generated during the production process of the emulsified modified bitumen equipment is very limited, reducing air pollution.
    The emulsified modified bitumen equipment sends the modified material manually poured into the dumping bin to the bitumen batching tank by wind or spiral. It can be equipped with a metering and calibration system. The emulsified modified bitumen equipment thickener is automatically or manually added. The emulsified modified bitumen equipment can be equipped with a metering and calibration system. Emulsified modified bitumen equipment transportation and metering and calibration system, the emulsified modified bitumen equipment adds the set bitumen amount to the batching tank through the frequency converter and computer interlock. The emulsified modified bitumen equipment and bitumen steam flowmeter use big brand products to ensure the preparation.

    Asphalt spreader is used to spread the penetration oil, waterproof layer and bonding layer of the bottom layer of asphalt pavement of high-grade highway. It can also be used for the construction of county and township highway oil roads with layered paving technology. It consists of a car chassis, an asphalt tank, an asphalt pumping and spraying system, a thermal oil heating system, a hydraulic system, a combustion system, a control system, a pneumatic system, and an operating platform.
    Knowing how to properly operate and maintain the asphalt spreader can not only extend the service life of the equipment, but also enable the construction project to proceed smoothly. So what problems should the asphalt spreader pay attention to when working? The technicians of Gaoyuan Road Construction Machinery Equipment Co., Ltd. give you tips:
    1). Before use, please check whether the position of each valve is accurate and make preparations before work. After starting the motor of the asphalt spreader, check the four thermal oil valves and the pressure gauge. After everything is normal, start the engine and the power take-off starts to work. Test the asphalt pump and circulate for 5 minutes. If the pump head shell is hot, slowly close the thermal oil pump valve. If the heating is insufficient, the pump will not turn or make noise. In this case, the valve needs to be opened to continue heating the asphalt pump until it can operate normally. During the working process, the asphalt liquid must be kept at a working temperature of 160~180℃, and it cannot be filled too full (pay attention to the liquid level pointer during the injection of asphalt liquid, and check the tank mouth at any time). After the asphalt liquid is injected, the filling port must be closed tightly to prevent the asphalt liquid from overflowing during transportation.
    2). During use, asphalt may not be pumped in. At this time, it is necessary to check whether the interface of the asphalt suction pipe is leaking. When the asphalt pump and pipeline are blocked by solidified asphalt, a blowtorch can be used for baking, and the pump must not be forced to turn. When baking, care should be taken to avoid directly baking the ball valve and rubber parts.
    3). When spraying asphalt, the car should be driven at a low speed. Do not step on the accelerator hard, otherwise it may cause damage to the clutch, asphalt pump and other components. If 6m wide asphalt is spread, pay attention to obstacles on both sides at any time to prevent collision with the spreading pipe. At the same time, the asphalt should be kept in a large circulation state until the spreading work is completed. After the work is completed every day, if there is any remaining asphalt, it must be returned to the asphalt pool, otherwise it will solidify in the tank and cannot work next time.
    4). In addition, the emulsifier must also pay attention to daily maintenance:
    1. The emulsifier and delivery pump and other motors, agitators, and valves should be maintained daily.
    2. The emulsifier should be cleaned after work every day.
    3. The speed regulating pump used to control the flow should be regularly tested for accuracy, and adjusted and maintained in time. The asphalt emulsifier should regularly check the matching clearance between its stator and rotor. When the minimum clearance specified by the machine cannot be reached, the stator and rotor should be replaced.
    4. If the equipment is out of use for a long time, the liquid in the tank and pipeline should be emptied (the emulsifier aqueous solution should not be stored for a long time), the hole covers should be tightly closed, kept clean, and the running parts should be filled with lubricating oil. When it is used for the first time or when it is used again after a long period of inactivity, the rust in the tank should be removed, and the water filter should be cleaned regularly.
    5. Regularly check whether the terminal in the electric control cabinet is loose, whether the wires are worn during shipment, and remove dust to avoid damage to the machine parts. The frequency converter is a precision instrument. Please refer to the instruction manual for specific use and maintenance.
    6. There is a heat transfer oil coil in the emulsifier water solution heating stirring tank. When injecting cold water into the water tank, the heat transfer oil switch should be turned off first, and then the switch should be turned on to heat after adding the required amount of water. Pouring cold water directly into the high-temperature heat transfer oil pipeline can easily cause the weld to crack.

    Bitumen decanter equipment can be placed in a complex system as an independent unit, replacing the existing heat source de-barreling method, or in parallel as a core component of a large set of equipment, or it can work independently to meet the requirements of small-scale construction operations.
    The Sinoroader bitumen decanter device is mainly composed of a de-barreling box, a lifting mechanism, a hydraulic thruster and an electrical control system. The box is divided into two chambers, the upper chamber is a barreled bitumen melting chamber, and heating coils are evenly distributed around it. The heating pipe and the bitumen barrel mainly exchange heat in a radiation manner to achieve the purpose of bitumen de-barreling. Several guide rails are the tracks for the bitumen barrel to enter. The lower chamber is mainly to continue heating the bitumen removed from the barrel to make the temperature reach the suction pump temperature (100℃), and then the asphalt pump is pumped into the upper chamber. At the same time, an empty barrel is pushed out at the rear end outlet. There is also an oil tank on the platform at the entrance of the asphalt barrel to prevent the dripping bitumen from flowing out.
    The inlet and outlet doors of the device adopt a spring automatic closing mechanism. The door can be automatically closed after the asphalt barrel is pushed in or out to reduce heat loss. A temperature gauge is installed at the asphalt outlet to observe the asphalt outlet temperature. The electrical control system can control the opening and closing of the hydraulic pump and the reversing of the electromagnetic reversing valve to realize the advance and retreat of the hydraulic cylinder. If the heating time is extended, a higher temperature can be obtained. The lifting mechanism adopts a cantilever structure. The bitumen barrel is lifted by an electric hoist, and then moved horizontally to place the bitumen barrel on the guide rail. A temperature gauge is installed at the outlet of the asphalt meltering equipment to observe its outlet temperature.

    The advantages of Sinoroader bitumen decanter equipment over similar domestic equipment are reflected in the following points:
    1. The equipment produces 8-10t/hour, with an automatic telescopic sealed container structure. It uses an electric hoist to lift the asphalt barrel at the inlet guide tube. Start to control the hydraulic cart forward button, which will promote the barrel push (push and slide into the barrel). It is a 1300mm hydraulic cylinder with a 7.5-ton top thrust. The device has a beautiful appearance, reasonable layout, compactness, stable performance, and is suitable for production under various industrial and mining conditions.
    2. Fast barrel removal: According to the principle of layered heating, it adopts four-layer thermal oil heating technology, a single inlet and outlet, and high thermal efficiency of heating; at the same time, it uses the waste heat of combustion gas for two heatings and efficient use of energy; the barrel body uses high-quality rock wool insulation material.
    3. Good environmental protection: closed structure, no pollution.
    4. No barrel hanging: The upper part of the asphalt barrel is hot, and each is directly affected by the thermal oil heating pipe. The barrel wall directly receives the heat dissipation of the heating coil, and the barrel is clean and fast, which will not cause waste of asphalt barrel hanging.
    5. Strong adaptability: Suitable for imported and domestic barrels, and the deformation of asphalt barrels will not affect production.
    6. Good dehydration: Use a large-displacement asphalt pump for internal circulation, stirring, water vapor overflows, and is naturally discharged from the exhaust port. After dehydration, asphalt can be directly used to produce asphalt mixture or used as matrix asphalt.
    7. Automatic slag removal: This set of equipment has an automatic slag removal function. The filter device sets the asphalt circulation pipeline through the filter, which can automatically remove the barreled asphalt slag.
    8. Safe and reliable: The equipment adopts an automatic control system, an automatic ignition burner import, can automatically control the temperature according to the temperature, and is equipped with corresponding monitoring instruments.
    9. Convenient relocation: The whole machine is assembled with large components, which is easy to move and quick to assemble.

    We have conducted in-depth research on asphalt distributors and have accumulated a lot of production technology experience. We have conducted professional and in-depth research on some problems existing in the market to provide convenience for everyone in future production applications.
    Every time when spraying asphalt, the asphalt distributor does not spray asphalt. Troubleshooting. The asphalt distributor does not spray asphalt. It is a common fault. The following teaches you how to solve the problem of not spraying asphalt.
    1. No asphalt spraying
    Analysis of the reasons may be the following reasons:
    1. Is the asphalt pump working?
    2. Are the valves adjusted correctly?
    3. Is the pump or pipeline blocked?
    2. Troubleshooting method
    1. Check whether the hydraulic system is working properly?
    2. After adjusting the valve position, the asphalt distributor must be cleaned to avoid pipeline blockage when used next time. Because the asphalt distributor has different high and low configurations, it can spread various high-viscosity and high-temperature modified asphalts and rubber asphalt in high configuration. If you mistakenly use a low-configuration asphalt truck to spread this type of asphalt, you must spray the asphalt inside the entire vehicle clean after the first use. After spraying, in order to leave no residual asphalt, you can use waste diesel to clean it. Our company’s vehicles are equipped with air cleaning and gravity cleaning devices. Diesel cleaning is a reliable cleaning method.