Home » Products » Asphalt Mixing Plant » Trial operation of asphalt mixer plant and its relationship with conveying pipe heating efficiency

Trial operation of asphalt mixer plant and its relationship with conveying pipe heating efficiency

Asphalt mixing plant is one of the main equipment for producing asphalt concrete. It can mix asphalt, gravel, cement and other materials together in a certain proportion to obtain the products required for highway construction. In order to ensure its operating effect, the asphalt mixer plant also needs to be powered on for trial operation before it is officially put into work.
At the beginning of the test run, first run a single motor, and at the same time check whether the current, steering, insulation and mechanical transmission parts are operating normally. After confirming that each motor and mechanical transmission parts are operating correctly, conduct a joint trial run. During the entire process, it is necessary to conduct patrol inspections of key parts. If any abnormal noise is found, the cause should be identified and eliminated in a timely manner.

Rated 4.6/5 based on 548 customer reviews
Share:
Content

Asphalt mixing plant is one of the main equipment for producing asphalt concrete. It can mix asphalt, gravel, cement and other materials together in a certain proportion to obtain the products required for highway construction. In order to ensure its operating effect, the asphalt mixer plant also needs to be powered on for trial operation before it is officially put into work.
At the beginning of the test run, first run a single motor, and at the same time check whether the current, steering, insulation and mechanical transmission parts are operating normally. After confirming that each motor and mechanical transmission parts are operating correctly, conduct a joint trial run. During the entire process, it is necessary to conduct patrol inspections of key parts. If any abnormal noise is found, the cause should be identified and eliminated in a timely manner.
After turning on the power, turn on the air compressor and let the air pressure reach the rated pressure value. During this process, you can clearly observe whether there is air leakage in the control valve, pipeline, cylinder and other components. Then connect the oil supply and return devices, oil supply and return pipelines, etc., and ensure that they do not leak. At the same time, use anti-rust components or take anti-rust measures.
Since the asphalt mixer plants contain many mechanical components, a complete set of commissioning operations requires consideration of all aspects, such as the hydraulic department, conveying mechanism, dust removal system, etc., and none of them can be left out. The heating efficiency of the asphalt conveying pipe of the asphalt mixing plant also has a great impact. This is because the important performance indicators of asphalt, such as viscosity and sulfur content, are closely related to the asphalt mixing plant.
Generally speaking, the greater the viscosity, the worse the atomization effect, which directly affects work efficiency and fuel consumption. As the temperature increases, the viscosity of heavy oil gradually decreases, so high-viscosity oil must be heated for smooth transportation and atomization.
Therefore, in addition to understanding its conventional indicators when selecting, you must also master its viscosity-temperature curve to ensure that heating can make the asphalt reach the viscosity required by the burner before atomization. When inspecting the asphalt circulation system, it was found that the asphalt in the pipeline solidified because the temperature of the asphalt transportation pipeline did not meet the requirements.

Inquiry


    More Asphalt Processing

    The asphalt mixing equipment mentioned here may also refer to an asphalt concrete mixing plant. At present, asphalt mixing equipment generally uses a complete set of equipment for mixing. So what are the benefits of using a complete set of equipment?
    1. More effective.
    In today’s industrial production, a complete set of asphalt mixing equipment can help improve production efficiency and ensure product quality. This is why even in a mixing plant, the equipment used is a complete set of equipment.
    2. Ensure quality.
    When mixing asphalt, a certain ratio is set. For this type of asphalt liquid used in different occasions, its ratio control has strict requirements. It is necessary to determine its mixing method and mixing time to ensure that the asphalt liquid is consistent with the production site. One of the advantages of a mixing plant is that the quality can be effectively controlled.
    3. It can be sampled.
    After mixing at the mixing plant, the quality inspector can sample and inspect to ensure that the mixed asphalt liquid meets the use requirements.
    In short, asphalt mixing equipment will use a complete set of equipment, mainly to facilitate the later asphalt to meet production needs. Through the mixing plant, the mixing time and feeding sequence can be better controlled, so that the mixed product can meet different use requirements. And after using the archiving equipment, effective spot checks can be carried out, which can better ensure that the quality meets the construction requirements.

    Judging from the situation of highways in our country, asphalt pavement is the most used, which is one of the reasons why asphalt mixing plants have developed so rapidly. Under the situation of rapid economic development, the quality problems of asphalt pavement are gradually increasing, which puts forward higher and higher requirements for the quality of asphalt. It is understood that the primary factor that affects the quality of asphalt is the ratio of raw materials. This is also covered in the introduction of asphalt mixing stations. You can discuss it together.
    In order to obtain high-quality asphalt products, in addition to the asphalt mixing equipment meeting the requirements, selecting the appropriate asphalt mixture gradation type is also a top priority. According to my country’s current regulations, the maximum particle size of the asphalt mixture in the upper layer of the highway should not exceed half of the layer thickness; while the maximum particle size of the aggregate in the middle surface layer of asphalt mixture should not exceed two-thirds of the layer thickness; and the asphalt layer should not exceed half of the layer thickness. The maximum nominal aggregate size of the pavement structural layer mixture should not exceed one-third of the layer thickness.
    Based on this analysis, if an asphalt surface layer with a certain thickness is selected according to the above specifications, the particle size of the asphalt mixture aggregates will generally be larger, which will inevitably bring insurmountable construction difficulties to the construction of asphalt concrete pavement. After investigation, testing, analysis, and comparison, it can be seen that the lower layer has a wider choice, so the AG-201 gradation type can be used; while the selection of the upper layer mixture type is more difficult, and it is necessary to achieve a reasonable choice of this mix ratio. , on the one hand, we must examine as many aggregate resources as possible, and on the other hand, we must also consider the model of the mixing equipment.
    In order to ensure the quality of the project, strict selection and inspection of engineering materials must be carried out. Therefore, the selection and determination of raw materials should be based on the requirements for pavement structure and use quality, combined with the supply of floor materials, and inspection in accordance with the requirements of relevant test procedures, and then Select the best materials so that all technical indicators of the materials meet the specified technical requirements.

    Emulsified asphalt equipment plays an important role in road construction, and its production quality will directly affect the quality of facilities such as roads. In order to operate it better, we need to pay special attention to the following four points when applying emulsified asphalt equipment:
    1. Before spraying, the emulsified asphalt equipment must check whether the position of each valve is correct. The hot asphalt added to the emulsified asphalt equipment must reach an operating temperature of 160~180℃. For long-distance transportation or long working time, a heating device can be used for insulation, but it cannot be used as an oil melting furnace.
    2. When the asphalt in the emulsified asphalt equipment is heated by a burner, the asphalt height must exceed the upper plane of the combustion chamber, otherwise the combustion chamber will be burned.
    3. The emulsified asphalt equipment cannot be filled too full, and the fuel filler cap must be closed tightly to prevent asphalt from overflowing during transportation.
    4. This vehicle has two front and rear control consoles. When using the front control console, the switch must be turned to the front control. At this time, the rear control console can only control the lifting and lowering of the nozzle.
    I believe that through the above description, everyone will be more comfortable when using emulsified asphalt equipment in the future. As for the relevant operating matters of the equipment, I will introduce them to you here today. If you want to know more information, please pay attention to the next explanation.

    The actual operation steps of drying drum of asphalt mixing equipment: 1. Pay attention to routine inspection; 2. Proper operation steps; 3. Effective maintenance.
    Drying drum is a cylindrical device specially used for heating and drying stones in asphalt mixing equipment. Proper application and maintenance of drying drum can maximize the performance of drying drum, increase its service life and reduce application cost. Let’s take a look at the actual operation steps below.
    1. Pay attention to routine inspections
    The asphalt mixing equipment drying drum has been tested and inspected before leaving the factory, but it will be subjected to vibration and vibration during transportation to the construction site. A comprehensive inspection should be carried out before use: check whether all anchor bolts are tightened; whether all key pins are properly driven; whether all drive devices are adjusted according to the manufacturer’s instructions; whether all pipe connections are appropriate and whether the three-way joints are reliable; whether the entire equipment is fully lubricated; start the motor and check whether all parts can rotate steadily in the correct rotation direction; whether the pressure gauge can work normally and whether the valve is adjusted to the correct working pressure; whether the burner ignition mechanism is available and whether the gate valve is open.
    2. Correct operation steps
    After the equipment is started, it is recommended to control the machine manually at the beginning, and then switch to the automatic control mode after achieving the required production volume and pouring temperature. The stone should be dried and have a stable moisture content as much as possible so that the stone can maintain a stable final temperature when passing through the drying drum. If the stones delivered to the drying drum change frequently and the moisture content changes each time, the burner should be adjusted frequently to compensate for these changes.
    The stones directly from the crushed stone have a relatively constant moisture content, while the stones from the outdoor storage yard have a higher moisture content, and the moisture content of different piles varies greatly. Therefore, it is best for the stones to come from the same source.