Asphalt Processing

Asphalt concrete, as the name implies, is a composite material formed by combining asphalt and concrete. Its main components usually include three categories, aggregate, filler and asphalt. Aggregate, as the basic skeleton of asphalt concrete, is mainly composed of crushed stones of different sizes. These crushed stones are carefully selected and proportioned to ensure the strength and stability of asphalt concrete. Filler usually refers to fine-grained materials such as stone powder, which are filled between crushed stones to increase density and improve overall strength. Asphalt is a binder that can tightly bond aggregate and filler together to form a solid whole. In the process of producing asphalt concrete, the proportion of various raw materials will be adjusted according to different formulas. These formulas are usually formulated according to the specific requirements of the road and the use environment to ensure that asphalt concrete can meet various complex road conditions. The place where this composite material is produced is a special asphalt mixing plant. This is an asphalt concrete mixing plant. The large trucks that we see every day to transport asphalt concrete come out from here. In the asphalt mixing plant, the entire production process is finely divided into multiple steps.
First, workers use loaders to deliver aggregates into cold silos. Cold silos are usually divided into several different chambers according to the size of aggregate particles, and each chamber corresponds to aggregates of different specifications. In this way, in the subsequent mixing process, the proportion of various aggregates can be accurately adjusted according to customer needs.
Next, these aggregates will be sent to the drying drum through a vibrating feeder and a belt conveyor. In the drying drum, the aggregates will be heated to a specified temperature by the high-temperature heat source provided by the burner. During this process, the spiral blades and sheep feed plates inside the drum will ensure that the aggregates are fully heated during rotation and remove the moisture in them. In this way, not only can the bonding strength between aggregates and asphalt be improved, but also the stability and durability of asphalt concrete after paving can be ensured.

The actual operation steps of drying drum of asphalt mixing equipment: 1. Pay attention to routine inspection; 2. Proper operation steps; 3. Effective maintenance.
Drying drum is a cylindrical device specially used for heating and drying stones in asphalt mixing equipment. Proper application and maintenance of drying drum can maximize the performance of drying drum, increase its service life and reduce application cost. Let’s take a look at the actual operation steps below.
1. Pay attention to routine inspections
The asphalt mixing equipment drying drum has been tested and inspected before leaving the factory, but it will be subjected to vibration and vibration during transportation to the construction site. A comprehensive inspection should be carried out before use: check whether all anchor bolts are tightened; whether all key pins are properly driven; whether all drive devices are adjusted according to the manufacturer’s instructions; whether all pipe connections are appropriate and whether the three-way joints are reliable; whether the entire equipment is fully lubricated; start the motor and check whether all parts can rotate steadily in the correct rotation direction; whether the pressure gauge can work normally and whether the valve is adjusted to the correct working pressure; whether the burner ignition mechanism is available and whether the gate valve is open.
2. Correct operation steps
After the equipment is started, it is recommended to control the machine manually at the beginning, and then switch to the automatic control mode after achieving the required production volume and pouring temperature. The stone should be dried and have a stable moisture content as much as possible so that the stone can maintain a stable final temperature when passing through the drying drum. If the stones delivered to the drying drum change frequently and the moisture content changes each time, the burner should be adjusted frequently to compensate for these changes.
The stones directly from the crushed stone have a relatively constant moisture content, while the stones from the outdoor storage yard have a higher moisture content, and the moisture content of different piles varies greatly. Therefore, it is best for the stones to come from the same source.

Bitumen is a polymer mixture composed of asphaltene, colloid, aromatic hydrocarbons and saturated hydrocarbons. Asphaltene is dispersed in aromatic hydrocarbons and saturated hydrocarbons with the help of colloid to form a colloidal structure. When the asphaltene content is low, the bitumen has good adhesion, plasticity and fluidity, but poor temperature stability and elasticity
Bitumen modification principle:
Bitumen is a polymer mixture composed of asphaltene, colloid, aromatic hydrocarbons and saturated hydrocarbons. Asphaltene is dispersed in aromatic hydrocarbons and saturated hydrocarbons with the help of colloid to form a colloidal structure. When the asphaltene content is low, the bitumen has good adhesion, plasticity and fluidity, but poor temperature stability and elasticity. The polymer modifier is similar to the asphaltene in bitumen. Its addition, after fully swelling with bitumen, absorbs the aromatic hydrocarbons and colloid in bitumen to form a new colloid, which not only retains or increases the adhesion, plasticity and fluidity of the original bitumen, but also improves the temperature stability and elasticity of bitumen, thereby achieving the purpose of improving the road performance of bitumen.
Bitumen modification process:
The modifier and additive are evenly and finely dispersed into the matrix bitumen, and the contact area between the original bitumen and the modifier is increased as much as possible to ensure full swelling and development, which not only improves the utilization rate of the modifier but also makes the original bitumen performance the most perfect improvement.
The modified bitumen complete production equipment has the following advantages:
1. It is suitable for a variety of modifiers, such as SBS, EVA, PE, etc.;
2. The ratio of modifier to bitumen can be set at any time according to user needs;
3. The production volume of each cycle can be set arbitrarily within the maximum productivity;
4. The modified bitumen has high quality, and the modifier has a small particle size and uniform distribution after emulsification;
5. The production process is fully automatically controlled, and the production records can be queried at any time;
6. The weighing system is accurate in measurement, and the weighing error is less than 1%;

In highway construction, asphalt mixing station plays a vital role. As a kind of equipment integrating intelligence, high efficiency and environmental protection, asphalt mixing station provides strong support for improving the quality of highway construction. This article will introduce the relevant knowledge of asphalt mixing station in detail to help readers understand this key equipment.
Asphalt mixing station is a kind of equipment specially used for producing asphalt concrete, which is widely used in highway, municipal road, bridge and other engineering construction. Asphalt concrete is a kind of building material mixed with asphalt, gravel, sand and other materials. It has the characteristics of strong durability and good compressive resistance. It is an ideal material for highway construction.
2. Features
Intelligence: Asphalt mixing station is equipped with advanced control system and sensor, which can realize automatic production, reduce manpower input and improve production efficiency.
Environmental protection: Asphalt mixing station adopts closed design to reduce dust pollution, and is equipped with noise reduction facilities to reduce noise pollution.
Efficiency: Asphalt mixing station has high production capacity and can produce a large amount of asphalt concrete in a short time to meet the needs of engineering construction.
3. Function
Provide asphalt concrete: The main function of asphalt mixing station is to produce asphalt concrete and provide necessary building materials for highway construction.
Improve highway quality: By using asphalt concrete, the smoothness, compressive strength and durability of the highway can be improved, thereby improving the quality of the highway.

Never stop, escorting the quality of road construction
Inheriting decades of technical accumulation, asphalt mixing station has become an indispensable part of building and maintaining high-level roads. This seemingly ordinary device carries the important mission of ensuring road safety and improving driving experience. As the core technology of modern road engineering construction, asphalt mixing station goes all out to continuously strive for a better, safer and more efficient travel environment.
Fast drive, tenacious progress
Asphalt mixing station plays a role in road engineering. It uses mature technology and processes to ensure the smooth progress of road construction with efficient mixing capacity and stable production quality. From conveying raw materials to the precise proportion of oil and aggregates, to the uniform mixing of the final product, the asphalt mixing station, with its professional working attitude, ensures the quality and stability of road materials, and provides a solid foundation for the construction of high-standard road projects.
Innovation leads, environmental protection takes the lead
Asphalt mixing station plays an important role in promoting sustainable development. Faced with increasingly urgent environmental protection requirements, mixing stations continue to innovate technology, improve production efficiency, and also pay attention to environmental protection responsibilities. By introducing advanced dust removal and purification devices, intelligent equipment control systems and combustion equipment, the asphalt mixing station effectively reduces environmental pollution and makes positive contributions to protecting the surrounding ecological environment.

Emulsified asphalt equipment plays an important role in road construction, and its production quality will directly affect the quality of facilities such as roads. In order to operate it better, we need to pay special attention to the following four points when applying emulsified asphalt equipment:
1. Before spraying, the emulsified asphalt equipment must check whether the position of each valve is correct. The hot asphalt added to the emulsified asphalt equipment must reach an operating temperature of 160~180℃. For long-distance transportation or long working time, a heating device can be used for insulation, but it cannot be used as an oil melting furnace.
2. When the asphalt in the emulsified asphalt equipment is heated by a burner, the asphalt height must exceed the upper plane of the combustion chamber, otherwise the combustion chamber will be burned.
3. The emulsified asphalt equipment cannot be filled too full, and the fuel filler cap must be closed tightly to prevent asphalt from overflowing during transportation.
4. This vehicle has two front and rear control consoles. When using the front control console, the switch must be turned to the front control. At this time, the rear control console can only control the lifting and lowering of the nozzle.
I believe that through the above description, everyone will be more comfortable when using emulsified asphalt equipment in the future. As for the relevant operating matters of the equipment, I will introduce them to you here today. If you want to know more information, please pay attention to the next explanation.

The drying drum of the asphalt mixing plant should pay attention to daily inspection, correct operation and reasonable maintenance, so as to extend its service life and reduce the cost of engineering use.
1. Pay attention to daily inspection. Before the asphalt mixing plant officially works, the drying drum needs to be tested and inspected to see whether each pipeline is reliably connected, whether the lubrication of the whole machine is feasible, whether the motor can be started, whether the functions of each pressure valve are stable, whether the instrument is normal, etc.
2. Correct operation of the mixing station. At the beginning of the asphalt mixing plant, manual operation can only switch to automatic control after reaching the specified production capacity and discharge temperature. The aggregate should be dry and have a standard mode so that it can maintain a constant temperature when flowing through the drying drum. When the entire aggregate is sent to dry, the moisture content will change. At this time, the burner should be used frequently to compensate for the change in moisture. During the rolling stone processing, the amount of water directly formed is basically unchanged, the amount of combustion accumulation increases, and the amount of water in the deposited accumulation material may change.
3. Reasonable maintenance of the asphalt mixing plant. Aggregates should be deactivated when the asphalt mixing plant is not in operation. After work every day, the equipment should be operated to discharge the aggregate into the dryer. When the material in the hopper leaves the combustion chamber, the combustion chamber should be closed and allowed to idle for about 30 minutes to cool down, so as to reduce its impact or make the machine run in a straight line. Install the drying cylinder fixing ring on all rollers synchronously.

The materials used in asphalt mixtures contain a lot of dust. When the equipment is operating, if the dust enters the atmosphere, it will cause pollution. Therefore, dust removal equipment must be installed, and now bag dust removal is the main method. Safety is a common sense issue. There are well-established standard safety rules.
Do not clean, oil or adjust any mechanical equipment that is not specifically explained during operation; turn off the power and lock it before inspection or repair activities to prepare for accidents. Because each situation has its own particularity. Therefore, be vigilant about safety damage issues, incorrect operation issues and other deficiencies. All of them may lead to accidents, personal injuries, reduced production efficiency, and more importantly, loss of life. Careful and early prevention is the best way to avoid accidents.
Careful and correct maintenance can make the equipment work more efficiently and control it within a certain level of pollution; the maintenance of each component should be carried out according to its operating standards; maintenance plans and safe operation procedures should be formulated according to the inspection and repair conditions that must be carried out.
Take out a work log to record all inspection and repair conditions, list the analysis of each inspection of each component and the description of the repair content or the date of the repair; the second step is to give the inspection cycle for each component, which should be determined according to the service life and wear condition of each component.

For road construction machinery, the following is mainly about the asphalt mixer in road construction machinery equipment. Because it is the key product of Wuxi road construction machinery manufacturers, it is necessary to carry out comprehensive training and mastery, so as to ensure meticulousness and practicality, and not ignore any knowledge points.
1. In road construction machinery, is there any difference between asphalt mixing equipment and asphalt concrete mixing equipment?
The answer given by Sinoroader Group manufacturer to this question is no, that is, there is no difference between asphalt mixing equipment and asphalt concrete mixing equipment. They refer to the same type of equipment, but they are different in name. It can be said that they are two names for the same type of equipment, and there is no difference in essence.
2. During the operation of the asphalt mixer, there is a sound in the mixing pot. What’s the matter?
In the view of Sinoroader Group, there are two answers to this question. One is that the mixer arm on the asphalt mixer is not good or damaged. The second is that the wear-resistant lining in the mixer is damaged, which leads to this problem.
3. What are the dust removal devices in the asphalt mixing equipment?
In the asphalt mixing equipment, for its dust removal device, Sinoroader Group believes that the key is to use the dry ash removal method, because it can facilitate the collection of raw materials. In terms of its dust removal equipment type, there are filter dust removal equipment, centrifugal fan dust removal equipment and force dust removal equipment, etc., which can all be used well.
For the asphalt mixer and asphalt mixing equipment in road construction machinery, I believe that through the practical discussion of the above relevant content, everyone can master it well and master it, so that in practice, they can have new gains and benefit a lot from it.

The renovation of the combustion-supporting system of the asphalt mixing plant and the use of DC frequency conversion CNC machining technology are all renovations of the original system. In addition to the above renovation plans, with the existing equipment and personnel, what other measures can be taken in the application to reduce the operating costs of concrete mixing plants?
At present, China has no mandatory national industry standards for heavy residual oil, and the quality of fuel oil varies greatly. Even from the same dealer, the quality difference between batches is very large, and it contains more residues. Therefore, bridge inspection equipment should be installed on the construction site, and professional personnel should inspect various performance parameters of gasoline and diesel to strictly control quality.
When the burner is working, if the flame of the combustion aid is red and the smoke from the ash removal chimney is black, this is the manifestation of poor atomization of gasoline and diesel and insufficient combustion aid. At this time, the following measures should be taken to deal with it: properly adjust the distance between the nozzle and the vortex plate, generally push it inward to a suitable distance, the purpose is to prevent the atomized oil cone sprayed from the nozzle from spraying into the vortex plate; effectively adjust the ratio of gasoline and diesel to gas, so that the gasoline and diesel increase the mass conversion law slowly, or the gas increase the mass conversion law quickly; promptly remove the carbon deposits and coke around the nozzle to prevent the flame from deflecting; heavy residual oil contains more residues, which can easily cause serious damage to the high-pressure oil pump and increase the working pressure, affecting the actual effect of atomization and the shape of the flame, so the high-pressure oil pump must be repaired or replaced in time; install metal filter devices in front of the first and second high-pressure oil pumps, and clean them frequently to prevent the residues in the gasoline and diesel from blocking the nozzle.
The operators should be trained in professional skills on a regular basis to strengthen their job responsibilities and moral education, so that they can establish their respective job responsibilities, understand the importance of their positions, understand the content of their work, and improve their professional level. Skilled operators can properly control the temperature of the asphalt mixing plant mixture to avoid gasoline and diesel waste.
In order to improve the combustion-supporting effect and effectively reduce the operating costs of asphalt mixing stations, Sinoroader Group kindly reminds that the following issues should be noted when using the burner in the asphalt mixing station: To improve the maintenance of the burner, the burner nozzle should be cleaned of charred materials and carbon deposits on the ignition electrode regularly. The nozzle can be disassembled according to the atomization status; the air-oil ratio of the burner is generally not adjusted, and the fuel pump pressure can be adjusted according to the smoke status and the temperature of the asphalt mixture; the sulfur dioxide generated by the combustion of light fuel oil has a strong corrosion to the bag, so the bag should be maintained regularly and the air pressure changes in the bag should be paid close attention to; water deashing will produce more foam, causing the sand settling tank to flow out, so the sand settling tank should be cleaned in time, and a watering design should be carried out to settle the foam; when the steam pressure decreases or the gear oil pump noise increases, the gear oil pump must be replaced.
When the burner is started, the fuel oil circulation system should be completed through the valve, and then the burner control box should be opened to start the burner. If the electronic ignition of the fuel oil fails, you can change the inlet tee and use the diesel engine for ignition. After the ignition is successful for 2 minutes, you can convert it into fuel oil. In this way, even the light fuel oil of lower quality can ensure combustion.

The actual operation steps of drying drum of asphalt mixing equipment: 1. Pay attention to routine inspection; 2. Proper operation steps; 3. Effective maintenance.
Drying drum is a cylindrical device specially used for heating and drying stones in asphalt mixing equipment. Proper application and maintenance of drying drum can maximize the performance of drying drum, increase its service life and reduce application cost. Let’s take a look at the actual operation steps below.
1. Pay attention to routine inspections
The asphalt mixing equipment drying drum has been tested and inspected before leaving the factory, but it will be subjected to vibration and vibration during transportation to the construction site. A comprehensive inspection should be carried out before use: check whether all anchor bolts are tightened; whether all key pins are properly driven; whether all drive devices are adjusted according to the manufacturer’s instructions; whether all pipe connections are appropriate and whether the three-way joints are reliable; whether the entire equipment is fully lubricated; start the motor and check whether all parts can rotate steadily in the correct rotation direction; whether the pressure gauge can work normally and whether the valve is adjusted to the correct working pressure; whether the burner ignition mechanism is available and whether the gate valve is open.
2. Correct operation steps
After the equipment is started, it is recommended to control the machine manually at the beginning, and then switch to the automatic control mode after achieving the required production volume and pouring temperature. The stone should be dried and have a stable moisture content as much as possible so that the stone can maintain a stable final temperature when passing through the drying drum. If the stones delivered to the drying drum change frequently and the moisture content changes each time, the burner should be adjusted frequently to compensate for these changes.
The stones directly from the crushed stone have a relatively constant moisture content, while the stones from the outdoor storage yard have a higher moisture content, and the moisture content of different piles varies greatly. Therefore, it is best for the stones to come from the same source.

The mobile forced asphalt mixing equipment adopts intermittent drying cylinder, double forced mixer, the main machine can be towed, small footprint, short installation cycle, convenient operation and maintenance, good stability, high degree of automation, high degree of standardization, and high quality of finished products, and the technology of continuous improvement. The mobile forced asphalt mixing plant is suitable for high-grade road asphalt paving and maintenance.
1. The combined structure of the drum dryer and the batching machine is installed on a movable bracket for easy movement.
2. The asphalt mixing plant is equipped with a double horizontal shaft to boil the aggregate and ensure uniform mixing.
3. In the densely arranged hanging barrels, the hot aggregate rises vertically. This lifting tool is easy to use and reliable.
4. For accurate weighing of aggregates, asphalt and powder ore, a measuring scale is used, which contains a weighing sensor for electronic measurement.
5. The movement of the power material follows a closed spiral path, which ensures little material loss and provides safe transfer.
6. On the cyclone burner, high-pressure oil is sprayed out and quickly atomized. In the combustion chamber, the material is fed in a spiral manner and automatically ignited by the oil mist, which ensures combustion efficiency. The cylindrical barrel of the burner is separated from the burner head. The furnace cavity can be pushed in and pulled out, which is convenient for replacing the damaged side column bricks inside the burner. The entire burner has a large heat capacity and high thermal strength. This is cost-effectiveness.